Cost per MWUnderstanding data center construction benchmarks

How campus scale, power density and procurement strategy influence construction costs across major US data center markets.

As investment in digital infrastructure accelerates, cost per megawatt has become one of the most widely referenced measures of data center development economics. Yet the apparent simplicity of the metric can obscure substantial differences in project scope, technical requirements and delivery strategy.

A rapidly evolving cost environment

According to JLL’s 2026 Global Data Center Outlook, average global data center construction costs increased from approximately $7.7 million per MW in 2020 to $10.7 million per MW in 2025.

JLL forecasts a further 6% increase in 2026, taking the average to approximately $11.3 million per MW.

This growth reflects sustained demand for new capacity, increasing technical complexity, constraints on skilled labor and longer procurement lead times.

However, these figures should not be interpreted as universal development costs. Benchmarking requires a consistent definition of scope, particularly when distinguishing base-building infrastructure from tenant technology and IT equipment.

How costs compare across US markets

JLL’s 2026 research identifies the following indicative construction cost ranges for major US data center markets:

MarketConstruction cost per MW
Chicago$12M–$14M
Northern Virginia$11M–$12M
Dallas$10M–$11M
Phoenix$10M–$11M
Atlanta$10M–$11M
Source: JLL 2026 Global Data Center Outlook. Figures reflect a standardized, single-tenant, 50 MW air-cooled facility, excluding land acquisition and active IT equipment.

These benchmarks demonstrate meaningful regional differences, but they should be treated as reference points rather than direct estimates for a particular development.

Why the same MW capacity can produce different costs

Several factors can materially influence construction costs.

Power density and cooling strategy

The growth of AI workloads is increasing demand for high-density computing infrastructure and liquid-cooling systems.

JLL estimates that liquid-cooled facilities can carry a construction cost premium of approximately 10% compared with conventional air-cooled facilities.

Turner & Townsend has also identified a 7–10% US construction cost premium for AI data centers compared with traditional facilities of similar IT capacity.

Campus scale and phasing

Large campuses may benefit from repeatable building designs, standardized equipment and coordinated procurement.

However, scale does not automatically translate into lower unit costs. Power infrastructure, enabling works, phasing constraints and accelerated delivery schedules can offset potential economies.

Power availability

Grid connection timelines, utility upgrades and alternative power strategies increasingly influence both site selection and project viability.

For some developments, the timing and cost of securing sufficient power may have a greater impact on the investment decision than relatively modest differences in building construction costs.

Procurement and delivery strategy

Early equipment reservations, contractor capacity, design standardization and the sequencing of multiple buildings can all influence final costs.

For large programs, procurement decisions made at the campus level may create opportunities that would not be available through individual building packages.

The importance of comparing like for like

A credible cost-per-MW benchmark must establish what is included.

Key considerations include whether capacity is measured as IT load or another power measure, the extent of utility infrastructure, redundancy requirements, cooling technology, building configuration and whether costs include owner expenses or technology fit-out.

Without this consistency, comparisons between projects can produce misleading conclusions.

Beyond a single benchmark

For owners and developers managing multiple facilities, the greatest value comes from connecting cost-per-MW benchmarks with detailed project data.

Tracking changes in equipment pricing, building systems, procurement packages and regional trade costs allows teams to understand not only whether a project is above or below benchmark, but why.

The Dharam perspective

As data center programs become larger and more technically complex, effective benchmarking requires a consistent, transparent cost structure. Combining detailed cost planning with historical project intelligence and digital analytics can support stronger feasibility assessments, procurement decisions and capital allocation across multi-site programs.

Market intelligence

More insights

  • Market report | National | Q3 2026 | 5 min read

    US construction escalation outlook

    Where tender pricing is moving and what owners should carry in budgets for the next four quarters.

    Read insight
  • Market report | Northeast | 2026 | 5 min read

    Labour availability and trade capacity

    Why trade coverage, bid list depth and specialist workforce availability are increasingly important to construction costs and project delivery.

    Read insight
  • Sector intelligence | Higher Education | October 2026 | 5 min read

    Higher education capital planning

    Why universities are rethinking capital priorities as deferred maintenance, aging facilities and funding pressures reshape campus investment.

    Read insight

Clearer decisions for complex projects.

Tell us about your project and the decision ahead. We’ll connect you with the right senior team and relevant experience.

Discuss a Project

Discuss a project

Tell us about your project.

Careers

Introduce yourself.

We use your details only to consider you for roles at Dharam Consulting, and keep applications for up to 12 months. To have yours deleted sooner, email careers@dharamconsulting.com.